Turkish Law in EnglishTÜRKİYE
Zoning Law (Law No. 3194)

Provisional Article 25

Chapter Six: Provisions Relating to the Bosphorus Law No. 2960

Added: 10/6/2022, Law No. 7410, Art. 10

For the incomplete buildings on parcels where, before the date on which this article enters into force, construction was started after obtaining a permit for more than one building and a construction servitude was established, but whose initial permit became void due to expiry of time before some of them were completed, in new permit applications to be made without any change in the building projects, except for changes that must be made for earthquake safety in the approved structural (static) project annexed to the permit, the consent of all the owners of the relevant building for which the permit application is made shall be required.

Entry into force:

Original Turkish text

GEÇİCİ MADDE 25

(Ek:10/6/2022-7410/10 md.)

Bu maddenin yürürlüğe girdiği tarihten önce, birden fazla yapı için ruhsat alınarak inşaata başlanmış ve kat irtifakı kurulmuş ancak bir kısmı tamamlanmadan süre nedeni ile ilk ruhsatı hükümsüz hale gelmiş olan parsellerdeki eksik kalan yapılar için; ruhsat eki onaylı statik projesinde deprem güvenliği bakımından yapılması zorunlu olan değişiklikler hariç, yapı projelerinde herhangi bir değişiklik olmaksızın yapılacak yeniden ruhsat başvurularında, ruhsat başvurusunda bulunulan ilgili yapı maliklerinin tamamının muvafakati aranır.

Yürürlük:

Text as of 1 October 2026 · Official source (Turkish): mevzuat.gov.tr ↗

Unofficial translation for information only. The Turkish text published in the Official Gazette is the only authoritative version. This page is not legal advice.