Added: 8/1/2002, Law No. 4736, Art. 2
Where it is documented that one or more infrastructure services such as roads, water, sewerage and natural gas have been provided by municipalities to structures for which an occupancy permit has not been granted or obtained, electricity, water and/or telephone may be connected temporarily until an occupancy permit is obtained, provided that the technical requirements have been fulfilled in line with the relevant regulations and upon an application made within six months from the date of publication of this Law.
The connection of electricity, water and/or telephone under this Article shall not constitute any acquired right.
Original Turkish text
GEÇİCİ MADDE 10
(Ek : 8/1/2002 – 4736/2 md.)
Kullanma izni verilmeyen ve alınmayan yapılara belediyelerce yol, su, kanalizasyon, doğalgaz gibi alt yapı hizmetlerinin birinin veya birkaçının götürüldüğünün belgelenmesi halinde ilgili yönetmelikler doğrultusunda fenni gereklerin yerine getirilmiş olması ve bu Kanunun yayımı tarihinden itibaren altı ay içerisinde baş vurulması üzerine kullanma izni alınıncaya kadar geçici olarak elektrik, su ve/veya telefon bağlanabilir.
Bu madde kapsamında elektrik, su ve/veya telefon bağlanması herhangi bir kazanılmış hak teşkil etmez.